Precision MEP estimation and fire sprinkler relocation for a specialised interior fitout within an existing operations centre, requiring DDA-compliant amenities, fire sprinkler coordination and minimal disruption to active building services.
Calibarium MEP was engaged to provide a detailed MEP estimation for the interior fitout of a specialised operations centre within an existing multi-storey building. This was a precision fitout, compact in footprint but complex in coordination, requiring DDA-compliant amenities, fire sprinkler modification across 73 heads, and careful integration with the building's existing hydraulic and fire infrastructure.
Fitout-specific challenge: unlike new-build projects, this fitout required working within existing ceiling voids, riser shafts and live building services, making accurate coordination between new plumbing, drainage and fire sprinkler modifications critical to avoiding clashes and costly delays.
| Fixture | Specification | Qty |
|---|---|---|
| Disabled Basin | DDA compliant, lever taps | 2 |
| Disabled WC | DDA compliant, grab rails | 2 |
| Sink / Dishwasher | Kitchenette connection | 2 |
| Component | Specification | Qty |
|---|---|---|
| Concealed Space Sprinklers | Relocated to suit new ceiling | 45 |
| Semi-Recessed Pendant Heads | New installation | 28 |
| Fire Hose Reel | Relocated | 1 |
| Fire Extinguishers | Dry & wet chemical (kitchen) | 3 |
Calibarium MEP delivered a precise fitout estimation that balanced the compact scope with the complexity of working within an existing building envelope. The fire sprinkler modification scope, spanning 73 heads, demonstrated our ability to coordinate new partition layouts with existing fire protection infrastructure while maintaining uninterrupted AS 2118 coverage.