Large-scale fire sprinkler and hydrant estimation for a premium Brisbane CBD commercial tower, featuring 500+ sprinkler heads, multi-zone hydrant coverage and butterfly valve controlled riser systems across two major floor levels.
Calibarium MEP was engaged to deliver a comprehensive fire protection estimation for a prestigious commercial high-rise tower in Brisbane's CBD. This flagship project required deep expertise in high-rise fire engineering, spanning multi-zone sprinkler systems, hydrant infrastructure with butterfly valve isolation, and precise riser calculations through multiple floor levels.
The scope focused on fire services across two major floor levels, with over 500 sprinkler heads, 907 linear metres of 25 mm sprinkler pipe, and a full hydrant network using pipe diameters from 40 mm through to 150 mm. The complexity of the high-rise environment demanded meticulous level-by-level quantification and riser coordination.
High-rise complexity: CBD high-rise fire protection demands absolute precision. Every sprinkler head must meet maximum spacing and distance-from-wall requirements per AS 2118.1, while hydrant coverage must satisfy AS 2419.1 for buildings exceeding 25 metres in effective height.
The sprinkler system was designed with multiple head types to suit different ceiling configurations and fire risk profiles:
| Sprinkler Head Type | Specification | Qty |
|---|---|---|
| Brass Pendant, 79°C | 10 mm orifice, standard response | 240 |
| Flush Ceiling, 68°C | 15 mm orifice, aesthetic integration | 248 |
| Brass Conventional, 68°C | 15 mm orifice, plant / service areas | 10 |
| Brass Horizontal Sidewall, 141°C | 15 mm orifice, high-temp zones | 3 |
| Diameter | Level 21 | Level 22 | Riser | Total |
|---|---|---|---|---|
| 25 mm | 194 lm | 369 lm | 97 lm | 660 lm |
| 32 mm | 28 lm | 56 lm | 7 lm | 91 lm |
| 40 mm | 55 lm | 32 lm | 5 lm | 92 lm |
| 50 mm | 4 lm | n/a | n/a | 4 lm |
| Component | Specification | Qty |
|---|---|---|
| Fire Hydrants | Internal landing valves | 6 |
| FH Pipe, 80 mm | Main floor distribution | 46 lm |
| FH Pipe, 100 mm | Riser / main trunk | 4 lm |
| FH Pipe, 65 mm | Branch connections | 6 lm |
| FH Pipe, 150 mm | Riser main | 4 lm |
| Butterfly Valves | Zone isolation | 2 |
| Fire Services Connection | Street main connection | 1 |
This project stands as one of Calibarium MEP's flagship fire protection estimations. The sheer scale, over 500 sprinkler heads and nearly a kilometre of sprinkler piping across just two levels, underscores the complexity of CBD high-rise fire engineering. Our detailed level-by-level quantification, combined with precise riser calculations and multi-temperature head selection, delivered an estimation package that enabled confident procurement, competitive tendering and compliant fire safety outcomes.
Accurate, code-compliant estimation packages for complex builds across Australia.